As of May 14th, 2021, the following works are being carried out: plastering works in the apartments of the entrance group are 100% completed.
Facade works are being carried out: from the 1st to the 24th floor - 95% of the work on the installation of translucent structures has been completed. Arrangement of the hinged ventilated facade from the 3rd to the 24th floor - works are 75% completed.
Sewerage and water supply works have been completed: water supply, sewerage and heating risers. Works on diluting the heating in the floor of the apartments: from the 3rd to the 24th floor are completed 100%.
Works on arrangement of cement-sand screed: from the 3rd to the 18th floor - 100%, the 19th - 40%, from the 20th to the 22nd floor - 100%.
Tiling of common areas: from the 3rd to the 15th floor - 100%, 16th - 90%, 17th - 60%, 18th - 90%, 20th - 60%.
Installation of apartment doors and doors in technical rooms - from the 3rd to the 18th floor - works are completed on 100%, the 20th and 21st - 100%.
Works on installation of heating radiators in apartments are completed from the 3rd to the 15th floor on 100%.
Electrical works: works are carried out to dilute the lighting of public places, from the 3rd to the 22nd floor - the work is done 100%. Works on laying power inputs in the apartment from the 3rd to the 22nd floor are completed.
Work is underway to install a fire alarm: 80% completed.
Work on the installation of elevator equipment is being completed - 90%.
Connection of external networks: water supply and sewerage systems - the work is 100% completed.
In the basement works on installation of individual heating point - are completed 90%, installation of the pumping station - 90%.
Arrangement of the roof of the house is completed at 20%.
In the parking lot №5 works on installation of the ventilation and smoke removal system are carried out - works are executed on 90%. Works on wiring of electric networks are carried out - 90%. The roof of the parking lot is 100% completed.