As of August 11, 2021, the following facade works are being carried out: arrangement of the hinged ventilated facade from the 1st to the 24th floor - works are executed on 100%.
Sewerage and water supply works have been fully completed: water supply, sewerage and heating risers. Works on diluting the heating in the floor of the apartments: from the 3rd to the 24th floor are fully completed.
Tiling of common areas: from the 3rd to the 24th floor - 100%. Finishing the walls of public places: from the 3rd to the 22nd floor executed on 100%, from the 23rd to the 24th - 50%.
Installation of apartment doors and doors in technical rooms - the work is done 100%.
Works on installation of heating radiators in apartments are executed from the 3rd to the 23rd floor on 100%.
Electrical work: work is underway to install lighting for public areas, from the 3rd to the 22nd floor - the work is executed on 100%. Works on laying power supply inputs to the apartment from the 3rd to the 23rd floor are fully completed.
Work is underway to install a fire alarm: 90% completed.
The installation of elevator equipment is 100% completed. Commissioning works are underway.
Connection of external networks: water supply and sewerage systems - the work is 100% completed.In the basement, work was carried out on the installation of an individual heating station (ITP) and the installation of a pumping station.
Arrangement of the roof of the house is completed 100%.
Finishing work on the entrance group is performed by 60%. Landscaping around 9 buildings- the work is done 100%. Landscaping of the area around the 9th house is executed on 50%.
In the parking lot №5 works on the installation of ventilation and smoke removal system - completed 100%. The work on the construction of power grids was fully completed. The roof of the parking lot is 100% completed. Floor arrangement - executed on 100%. Marking of parking places is also completed.