August 11, 2021

Report on the construction of the 9th building and parking lot №5 of the residential complex "RiverStone"

No items found.

As of August 11, 2021, the following facade works are being carried out: arrangement of the hinged ventilated facade from the 1st to the 24th floor - works are executed on 100%.

Sewerage and water supply works have been fully completed: water supply, sewerage and heating risers. Works on diluting the heating in the floor of the apartments: from the 3rd to the 24th floor are fully completed.

Tiling of common areas: from the 3rd to the 24th floor - 100%. Finishing the walls of public places: from the 3rd to the 22nd floor executed on 100%, from the 23rd to the 24th - 50%.

Installation of apartment doors and doors in technical rooms - the work is done 100%.

Works on installation of heating radiators in apartments are executed from the 3rd to the 23rd floor on 100%.

Electrical work: work is underway to install lighting for public areas, from the 3rd to the 22nd floor - the work is executed on 100%. Works on laying power supply inputs to the apartment from the 3rd to the 23rd floor are fully completed.

Work is underway to install a fire alarm: 90% completed.

The installation of elevator equipment is 100% completed. Commissioning works are underway.

Connection of external networks: water supply and sewerage systems - the work is 100% completed.In the basement, work was carried out on the installation of an individual heating station (ITP) and the installation of a pumping station.

Arrangement of the roof of the house is completed 100%.

Finishing work on the entrance group is performed by 60%. Landscaping around 9 buildings- the work is done 100%. Landscaping of the area around the 9th house is executed on 50%.

In the parking lot №5 works on the installation of ventilation and smoke removal system - completed 100%. The work on the construction of power grids was fully completed. The roof of the parking lot is 100% completed. Floor arrangement - executed on 100%. Marking of parking places is also completed.