As of June 14th, 2021, the following facade works are being carried out: from the 1st to the 24th floor - 100% of works on installation of translucent designs are executed. Arrangement of the hinged ventilated facade from the 3rd to the 24th floor - works are executed on 85%.
Sewerage and water supply works have been fully completed: water supply, sewerage and heating risers. Were executed on 100% the works on diluting the floor heating in the apartments: from the 3rd to the 24th floor.
Works on arrangement of cement-sand screed: executed on 100%Tiling of common areas: from the 3rd to the 18th floor - 100%, from the 20th to the 22nd - 100%. Finishing the walls of common areas: from the 4th to the 7th floor is executed on 80%.
Installation of apartment doors and doors in technical rooms - from the 3rd to the 18th floor - works are executed on 100%, the 20th and 23rd - 100%.
Works on installation of heating radiators in apartments are executed from the 3rd on the 15th floor on 100%.
Electrical works: work is underway to install lighting for public areas, from the 3rd to the 22nd floor - the work is executed on 100%. Works on laying power inputs in the apartments from the 3rd to the 23rd floor are completed.Work is underway to install a fire alarm: 80% completed.
Work on the installation of elevator equipment is being completed - 90%.
Connection of external networks: water supply and sewerage systems - the work is 100% completed.
In the basement works on installation of individual heating point (ITP) - are being executed on 90%, installation of pumping station - 90%.
Arrangement of the roof of the house is executed on 50%.
In the parking lot №5 works on installation of ventilation and smoke removal system are being carried out - works are executed on 90%. Works on wiring of electric networks are carried out - 90%. The roof of the parking lot is 100% executed. Floor arrangement - executed on 20%.