As of July 14, 2021, the following facade works are being carried out ...
Arrangement of the hinged ventilated facade from the 1st to the 24th floor - works are executed on 90%.
Sewerage and water supply works have been completed: water supply, sewerage and heating risers. Works on diluting the heating in the floor of the apartments: from the 3rd to the 24th floor have been completely executed.
Tiling of common areas: from the 3rd to the 18th floor - 100%, 19th floor - 20%, from the 20th to the 24th - 100%. Finishing the walls of public areas: from the 4th to the 14th floor - 100%, from the 15th to the 22nd - 80%.
Installation of apartment doors and doors in technical rooms - the work is done 100%.
Works on installation of heating radiators in apartments are executed from the 3rd on the 23rd floor on 100%.
Electrical works: works on lighting of public places are being carried out , from the 3rd to the 22nd floor - the work is done 100%. Works on laying power supply inputs to the apartments from the 3rd to the 23rd floor are completely executed.
Work is underway to install a fire alarm: 90% completed.
The installation of elevator equipment is 100% completed. Commissioning works are being carried out.
Connection of external networks: water supply and sewerage systems - the work is 100% completed.
In the basement works on installation of an individual heating point (IHP) - 100%, installation of a pumping station - 100%)
Arrangement of the roof of the house is completed 100%.
In the parking lot №5 works on installation of ventilation and smoke removal systems are being carried out - works are executed on 100%. The work on the construction of power grids was completely executed. The roof of the parking lot is 100% completed. Floor arrangement - 80% completed.