July 14, 2021

Report on the construction of the 9th building and parking lot №5 in the RiverStone residential complex

No items found.

As of July 14, 2021, the following facade works are being carried out ...

Arrangement of the hinged ventilated facade from the 1st to the 24th floor - works are executed on 90%.

Sewerage and water supply works have been completed: water supply, sewerage and heating risers. Works on diluting the heating in the floor of the apartments: from the 3rd to the 24th floor have been completely executed.

Tiling of common areas: from the 3rd to the 18th floor - 100%, 19th floor - 20%, from the 20th to the 24th - 100%. Finishing the walls of public areas: from the 4th to the 14th floor - 100%, from the 15th to the 22nd - 80%.

Installation of apartment doors and doors in technical rooms - the work is done 100%.

Works on installation of heating radiators in apartments are executed from the 3rd on the 23rd floor on 100%.

Electrical works: works on lighting of public places are being carried out , from the 3rd to the 22nd floor - the work is done 100%. Works on laying power supply inputs to the apartments from the 3rd to the 23rd floor are completely executed.

Work is underway to install a fire alarm: 90% completed.

The installation of elevator equipment is 100% completed. Commissioning works are being carried out.

Connection of external networks: water supply and sewerage systems - the work is 100% completed.

In the basement works on installation of an individual heating point (IHP) - 100%, installation of a pumping station - 100%)

Arrangement of the roof of the house is completed 100%.

In the parking lot №5 works on installation of ventilation and smoke removal systems are being carried out - works are executed on 100%. The work on the construction of power grids was completely executed. The roof of the parking lot is 100% completed. Floor arrangement - 80% completed.